Department Contacts





Up from the Ashes...Through Teamwork

Manatts' Fire Damaged HMA Components
While in the middle of a major Iowa I-80 project, Cedarapids customer Manatts, Inc. experienced a hot mix asphalt plant owner's worst nightmare. Near midnight one Monday, local fire authorities awakened Manatts' workers with bad news...their Menlo, Iowa plant (which was supplying hot mix asphalt for the interstate project) was on fire.

Early the next morning company president Brad Manatt drove to the site to survey the damage. The drum's slinger conveyor and burner, plus control house, scale conveyor and all power/control wiring were severely damaged. The cold feed bin system sustained minor damage.

With a 40 working day contract on the I-80 job, the company was obviously faced with an emergency situation. According to Brad Manatt, "We were probably looking at losing between $10,000-20,000 per day by having the site inoperable. We needed to do something quickly."

They relocated personnel from the Menlo work site to other locations to keep people busy, which added to their daily downtime costs. They also faced the possibility of a $1,200 per day penalty if the I-80 project wasn't completed on time.

Manatts Sends Out Distress Signal

On the day of the fire, Manatts alerted Cedarapids about the situation. Manatts immediately sent their company airplane to Cedar Rapids and flew Tom Hartshorn, Cedarapids' HMA product support manager, to the site to survey the damage.

Hartshorn advised the customer that it would be to their advantage to purchase new equipment rather than repair the damaged components. According to Hartshorn, "If Manatts had wanted us to undertake repairs it would have taken between four and six weeks. With the I-80 project essentially on hold due to the fire, performing such extensive repairs was just not a viable alternative."

Hartshorn informed Manatts that a new E400P Magnum CF® portable drum plant was immediately available. They were told that if they could assist with installation, the plant could be operational in one week.

Manatts flew to Cedarapids' Glasgow operations to look at the E400P and other replacement components. Less than two days after the fire, HMA national sales manager Reaburn King had supplied Manatts with a proposal. The deal was finalized late that day.

The following morning, Manatts had a fleet of six trucks en route to pick up the new equipment. By that evening all of the equipment had been loaded and was on its way back to Iowa. Jim Siefert, Cedarapids' field serviceman in charge, was at the Menlo site to direct the set up.

Early Friday, less than five working days after the fire, the equipment was unloaded. Manatts' personnel had been busy preparing the site during equipment purchase negotiations. Pre-erection of the plant at the factory ensured trouble-free installation.

Crews installed an E400P drum mixer with RAP collar, Magnum® 60,000 cfm baghouse, split-level control house with QMA 2001™ pushbutton control system, five cold feed bins and scale conveyor. The existing 80SE self-erecting storage silo and AC tank were spared damage by the fire.

Teamwork Makes the Impossible Possible

Cedarapids service personnel were dispatched from job sites throughout the country to help Manatts install the new equipment. Service crews worked virtually non-stop throughout the weekend, except to catch a few hours of sleep.

According to Steve Armstrong, Manatts general plant superintendent, "The overall level of professional service was exceptional. Without Cedarapids' support we would never have been able to stay on schedule with the I-80 project."

On Monday, June 28th, the plant was ready for calibration. By Wednesday the 30th, just a week after the order was signed, the plant was producing mix.

Manatt stated, "We are very fortunate that Cedarapids was immediately able to supply us with a portable plant. Close teamwork between their people and our own made it all possible."

From Cedarapids' viewpoint, expressed by Tom Hartshorn, "We were very pleased with the amount of cooperation Manatts provided. They assisted with getting the job done without interruption or delay. This was a major factor in getting their site operational in a matter of days."

Safe Practices Keep Problems at Bay

Commenting on the fire, Hartshorn said, "The fire had probably burned a couple of hours before a passerby noticed and alerted the local volunteer fire department. The remoteness of the site, along with the fact that the fire happened at night, had a large part to do with the amount of damage that occurred."

Prior to the fire, the customer had been using an older Cedarapids 8835 parallel flow drum mixer that used reclaimed fuel. The fuel was stored in a 9,500 gallon storage tank which utilized a heater to bring the fuel to the correct viscosity. It is suspected that a malfunction in the tank's heater caused the fuel in the tank to ignite. This in turn led to a leak in the fuel supply line running to the drum burner, which made matters worse.

Hartshorn noted, "This type of fire is a rarity. The storage tank was located between the control house and cold feed bins, with electrical cabling running directly over it. Having their storage fuel tank located further away from the other plant components might have eliminated the amount of damage."

Fire Prevention

Perhaps the first step to on-site fire prevention is having plant personnel properly trained. Keeping equipment in good repair and always being alert to what's going on are major factors in fire prevention. Good housekeeping is equally critical to preventing the possibility of fire, as is keeping a supply of filled and periodically checked fire extinguishers readily available.

Make sure that all equipment is properly shut down before leaving the site at night or for any extended period. Hartshorn noted, "Running engines and motors without plant personnel in attendance has its own inherent risks."

Site personnel also need to be aware of what to do and who to call in the event of a fire. Local fire authorities are happy to assist with any producer's efforts to better inform personnel about fire safety and control.

According to Hartshorn, "Computer plant automation controls installed on many HMA facilities do not typically have fire alert systems. Obviously, for stationary urban locations some form of fire warning system is advisable. Mounting sensors on the equipment is one solution."

Manatts New E400PManatts Dedicates New Facility

Manatts estimates that up to 80,000 tons of mix was used for the project, which included milling and overlaying a 12 mile section of the interstate's westbound lanes. Manatts was also contracted to repair off ramps and crossovers on the stretch.

Two inches of both binder and surface coarse mix were used.

The drum produced three types of Superpave mix: 19mm type B base, 19mm type A binder, and 19mm type A surface coarse.

After completion of the interstate job, the E400P was relocated to another major reconstruction project in Audubon County, Iowa. Here the new portable drum is providing an estimated 130,000 tons of mix for a section of Iowa Highway 71 North.

To formally dedicate the new Adair, County site, Manatts' personnel placed an American flag on the highest point of the plant. As is the custom at Manatts, a flag raising ceremony is held each time a new facility is put into operation -- evidence of their pride in being a United States contractor, and with their people and equipment.

Top of Page

 

Page updated 27 January, 2004


Copyright© 2004 Cedarapids, Inc. All rights reserved.
General Inquiries Contact: info@cedarapids.com
Legal notices

 


Copyright© 2004, Terex Corporation. All rights reserved.
Contac the webmaster